  1. Open the workspace selector by clicking on the three line menu icon in the upper left corner of the system.
      
  2. Select Attendance.
     
  3. Select Facility Check-in on the left panel.
    Image RemovedImage Added
  4. Select a Facility, if you have not done so already. 
    Image RemovedImage Added

  5. Double click on the date to enter in data.
    Image RemovedImage Added
  6. Use the tabs at the top to select the Time Frame as needed.
    Image RemovedImage Added
  7. Enter in data on the Count field using the Female Male Category and the Activity & Rank matrix or toggle "No Data" ON and enter a reason if nothing occurred that day. If you select "No Data" the Number of Players tab will gray out as well.
    Image Removed Click the "Save" button when complete.
    Image Removed

 

...

  1. Note: If there are several days without any Facility Check-ins you can enter in an End Date to create a range. This speeds up data entry, so you do not have to open up every day to toggle the "No Data" ON.
    Image AddedImage Added